Ranking projects for an electricity utility using ELECTRE III

International Transactions in Operational ResearchPublished 12 June 2007Open access
John Buchanan, Daniel Vanderpooten
Citations62
View PDF

TL;DR

This work describes a project selection methodology developed and used since 1998 for Mighty River Power, a New Zealand electricity generator, which incorporates the ELECTRE III decision support tool.

Abstract

Abstract Ranking and selecting projects is a common yet often difficult task with typically more than one dimension for measuring project impacts and more than one decision maker. We describe a project selection methodology developed and used since 1998 for Mighty River Power, a New Zealand electricity generator, which incorporates the ELECTRE III decision support tool. Although several other multiple criteria approaches could have been used, features of ELECTRE III such as outranking, and indifference and preference thresholds were well received by our decision makers. More than the use of a specific decision support tool, we focus particularly on the successful implementation of a simple, structured multicriteria methodology for a yearly project selection exercise and document this over 8 years in a changing managerial context.

Keywords

Decision SciencesEnvironmental Science